Legal Stuff: The information contained in the Builder's Log is for recreational use only and reflects my thoughts and opinions. It does not reflect the thoughts or opinions of my wife, my kids, my fish (if I had one and I do not), my car, or my computer. Do not try this at home. Beware of dog. As seen on TV. No substitutions allowed. Void where prohibited. No shirt, no shoes, no service. Quantities are limited. No one under 17 admitted. One at this price. No purchase necessary. You do not need to be present to win. Some assembly required. Batteries not included. Action figures sold separately. Apply only to affected area. May be too intense for some viewers. All models are over 18 years of age. Safety goggles must be worn at all times. Sealed for your protection. If a rash, redness, irritation, or swelling develops, discontinue use and consult your physician. Sanitized for your protection. Wash, rinse, repeat. May be hazardous to your health. We're not in Kansas any more. Slippery when wet. Edited for television. No animals were harmed in the making of this web site. No salt, MSG, or artificial color added. The white zone is for passenger loading and unloading only. Driver does not carry cash. Auto pilot is engaged during flight. Substantial penalties for early withdrawal. Allow four to six weeks for delivery. Other restrictions may apply. And as always, your mileage may vary.

 Log Sections
Planning, Shop & Equipment
Empennage
     Horizontal Stabilizer | Vertical Stabilizer | Rudder | Elevators
Wings
     Spars | Ribs | Wings | Fuel Tanks | Ailerons | Flaps
Fuselage
     Firewall | Bulkheads | Longerons | Aft Fuselage | Center Fuselage
     Forward Fuselage | Aft Deck, Canopy Decks & Top Skins | Cabin & Seats
Other Stuff


Planning, Shop & Equipment[TOP]

Planning   [TOP]
March 19-20, 2005 - Sportair Sheet Metal Workshop
May 12, 2005 - Trip to Van's, ordered Empennage

Shop & Equipment   [TOP]
February - May, 2005 - Built workshop
May 15, 2005 - Completed Worktable(s)
May 20, 2005 - Bought more Tools, DRDT-2 Arrives
May 21, 2005 - Built plans Holder/Hanger
May 23, 2005 - Cleveland, Brown Tools, and Band Saw
May 24, 2005 - More Tools Arrive
June 22, 2005 - Built Air Line Condenser
June 24, 2005 - Burraway Arrives
May 11, 2006 - Making Progress - Setting up Shop #2
May 13, 2006 - New Wing Jigs Started
May 21, 2006 - More (New) Shop Work
June 5, 2006 - Shop Wiring In Process
June 11, 2006 - Shop Wiring Complete!
February 1, 2007 - Project Update
July 15, 2007 - Shop Reorganization
August 15, 2007 - Engine Choices Made

Empennage[TOP]

Horizontal Stabilizer   [TOP]
May 19, 2005 - Empennage kit arrives, Inventory & Organize Parts - 2.5 hrs
May 26, 2005 - HS Construction Begins! - 2.0 hrs
May 29, 2005 - HS Rear Spar continues & Begin Front Spar - 3.5 hrs
May 30, 2005 - HS Rear & Front Spar Continues - 1.5 hrs
June 1, 2005 - Trim and Bend the HS-702s (HS Front Spars) - 1.75 hrs
June 8, 2005 - Trim the HS-404s, rough HS assembly - 2.0 hrs
June 12, 2005 - Assemble and Drill the Horizontal Stabs - 7.0 hrs
June 14, 2005 - Edge Finishing & Deburring - 2.5 hrs
June 16, 2005 - More Deburring - 2.0 hrs
June 17, 2005 - Dimpled Understructure - 2.0 hrs
June 18, 2005 - First Attempt at Priming - 4.0 hrs
June 26, 2005 - Priming & Deburring - 4.0 hrs
June 30, 2005 - Switched Primers & Recoat Parts - 2.0 hrs
July 1, 2005 - Dimple HS Skin - 0.5 hrs
July 2, 2005 - Rivet HS Rear Spar - 2.0 hrs
July 3, 2005 - Rivet HS Front & Rear Spars - 4.0 hrs
July 5, 2005 - Start Riveting Left HS Skin - 1.0 hrs
July 6, 2005 - Bad News from Vans - 1.0 hrs
July 12, 2005 - Replace HS-710, Edge Finishing & Dimpling the VS - 2.0 hrs
July 16, 2005 - HS Riveted... The Chair Flys! - 6.0 hrs

Vertical Stabilizer   [TOP]
July 8, 2005 - Started the VS - 4.0 hrs
July 11, 2005 - Deburring & Edge-Finishing on the VS - 2.0 hrs
July 12, 2005 - Replace HS-710, Edge Finishing & Dimpling the VS - 2.0 hrs
July 13, 2005 - Scrub & Clean the VS Parts - 1.0 hrs
July 14, 2005 - Etch & Prime the VS Parts - 1.0 hrs
July 17, 2005 - Rivet VS Spar & Dimple VS Skin - 1.5 hrs
July 19, 2005 - Prime VS-706 Rib - 1.0 hrs
July 20, 2005 - Rivet the VS - 3.0 hrs

Rudder   [TOP]
July 21, 2005 - Trim & Drill Rudder Stiffeners - 2.5 hrs
July 25, 2005 - Deburr & Dimple Rudder Stiffeners - 2.0 hrs
July 26, 2005 - Prime Rudder Stiffeners - 2.0 hrs
July 27, 2005 - Rivet Rudder Skins - Begin Skeleton - 1.5 hrs
July 28, 2005 - Drilling the Rudder - 2.5 hrs
July 30, 2005 - More Rudder Work - Drill, Deburr & Dimple - 3.5 hrs
July 31, 2005 - Still More Rudder - Deburr, Dimple & Countersink - 4.0 hrs
August 1, 2005 - Rudder Priming - 2.0 hrs
August 2, 2005 - Rivet the Rudder Skeleton - 2.5 hrs
August 3, 2005 - Rivet the Rudder Skins to the Skeleton - 2.5 hrs
August 6, 2005 - Glue Rudder Trailing Edge - 2.5 hrs
August 7, 2005 - Rivet the Rudder Trailing Edge - 1.0 hrs
August 8, 2005 - Bend the Rudder Leading Edge - 1.5 hrs
August 9, 2005 - Rivet the Rudder Leading Edge - 1.25 hrs

Elevators   [TOP]
August 13, 2005 - Trim & Drill Elevator Stiffeners - 5.0 hrs
August 15, 2005 - Dimple Stiffeners & Begin Elevator Skeleton - 1.5 hrs
August 17, 2005 - Dimple Elevator Skins & Start Trim - 1.5 hrs
August 18, 2005 - Scrubbed Elevator Stiffeners & Trim Parts - 1.0 hrs
August 19, 2005 - Primed Elevator Stiffeners & Trim Parts - 2.0 hrs
August 20, 2005 - Riveted Trim Parts & Elevator Stiffeners - 5.0 hrs
August 21, 2005 - Bent Elevator Trailing Edges - 2.0 hrs
August 23, 2005 - Fit & Drill New Elevator Ribs - 1.25 hrs
August 24, 2005 - Drilled the Right Elevator - 2.0 hrs
August 25, 2005 - Drilled the Left Elevator - 1.5 hrs
September 4, 2005 - Dimpled, Deburred & Primes R Elevator - 3.0 hrs
September 5, 2005 - Riveted Right Elevator Skeleton - 1.5 hrs
September 6, 2005 - Rivet Right Elevator Skeleton - 2nd Attempt - 1.0 hrs
September 8, 2005 - Countersunk, Deburr & Dimple L Elevator Skeleton - 1.5 hrs
September 10, 2005 - Fabricated Right Elevator Doubler - 1.5 hrs
September 11, 2005 - Elevator Trim & Edge-Finishing - 2.5 hrs
September 12, 2005 - Scrubbed Left Elevator Parts - 0.75 hrs
September 13, 2005 - Primed Left Elevator Parts - 1.5 hrs
September 14, 2005 - Rivet Right Elevator... Again!!! - 3.0 hrs
September 15, 2005 - Completed Right Elevator Riveting! - 2.0 hrs
September 18, 2005 - Riveted the Left Elevator - 5.0 hrs
September 26, 2005 - Bent Trim Tab Ends - 2.0 hrs
September 28, 2005 - Drilled Trim Tab - 2.0 hrs
October 5, 2005 - Primed Trim Tab Parts - 1.0 hrs
October 6, 2005 - Riveted Trim Tab - 3.0 hrs
October 13, 2005 - Trim Tab & Trim Motor Work - 2.0 hrs
October 19, 2005 - Bent (Rolled) Elevator Leading Edges - 1.5 hrs
October 23, 2005 - Rivet Right Elevator Leading Edge - 1.5 hrs
October 24, 2005 - Rivet Left Elevator Leading Edge - 0.75 hrs
November 29, 2005 - Trim Cover & Elevator Tabs Rework - 1.5 hrs
November 30, 2005 - Fabricated Elevator Tab Rib - 2.0 hrs
December 6, 2005 - Began Trim Tab II - The Sequel - 2.5 hrs
December 7, 2005 - Drilled & Deburred New Trim Tab - 1.0 hrs
December 11, 2005 - Primed Trim Tab Parts - 1.0 hrs
December 12, 2005 - Assembled New New Trim Tab - 2.0 hrs
December 14, 2005 - Mounted Elevators - 2.5 hrs
December 15, 2005 - Drilled Elevator Horns - 3.0 hrs


Wings[TOP]

July 22, 2005 - Wings Ordered!
September 29, 2005 - Wings Arrive!
October 3, 2005 - Wing Inventory - 1.0 hrs
October 4, 2005 - More Inventory - 2.0 hrs
October 5, 2005 - Still More Inventory & Organize - 1.0 hrs

Spars   [TOP]
October 15, 2005 - Countersunk Wing Spars - 4.0 hrs
October 16, 2005 - More Wing Spar Countersinking - 2.0 hrs
October 18, 2005 - Went Shopping for Wing Jig Supplies - 1.0 hrs
October 21, 2005 - Started Wing Jigs - 1.0 hrs
October 22, 2005 - Wing Jig Construction - 4.0 hrs
October 24, 2005 - More Wing Spar Countersinking - 1.5 hrs
October 25, 2005 - Wing Spar Countersinking, Priming & Tie-Downs - 2.0 hrs
October 26, 2005 - Drilled the Tie-Downs Brackets - 1.5 hrs
October 27, 2005 - Drilled & Prime Tie-Downs - 1.5 hrs
October 28, 2005 - Riveted & Installed Tie-Downs - 1.0 hrs
October 29, 2005 - Deburred & Trimmed Rear Spar Parts - 4.0 hrs
October 30, 2005 - Deburred, Drilled & Primed Rear Spars - 6.0 hrs
October 31, 2005 - Dimpled & Clecoed Rear Spars - 0.75 hrs
November 1, 2005 - Begun Rear Spar Riveting - 1.5 hrs
November 2, 2005 - Completed Rear Spar Riveting & Wing Jig - 1.5 hrs
November 4, 2005 - Completed Wing Jig - 2.0 hrs

Ribs   [TOP]
November 5, 2005 - Began Wing Rib Deburring - 2.0 hrs
November 6, 2005 - More Wing Rib Deburring - 2.0 hrs
November 8, 2005 - Still More Wing Rib Deburring - 1.5 hrs
November 10, 2005 - Even More Wing Rib Deburring - 2.0 hrs
November 11, 2005 - Completed Wing Rib Deburring! - 4.0 hrs
November 12, 2005 - Straightened Wing Rib Flanges - 3.0 hrs
November 15, 2005 - Wing Rib Fluting - 2.0 hrs
November 20, 2005 - More Wing Rib Fluting - 3.0 hrs
November 21, 2005 - Drilled Holes for Wing Conduit - 2.5 hrs
November 23, 2005 - Drilled Bushing Holes - 2.0 hrs

Wings   [TOP]
November 24, 2005 - Match-Drilled Left Wing Ribs/Spars - 1.0 hrs
November 25, 2005 - Match-Drilled Right Wing Ribs/Spars - 2.0 hrs
November 26, 2005 - Primed Wing Ribs - 5.0 hrs
November 28, 2005 - Ordered Wing Stuff - 0.0 hrs
December 1, 2005 - SafeAir1 Stuff Arrived - 0.0 hrs
December 5, 2005 - Wing Stuff from Van's Arrived - 0.0 hrs
December 18, 2005 - Riveted R Wing Skeleton - 5.0 hrs
December 19, 2005 - Began L Wing Skeleton - 3.0 hrs
December 21, 2005 - Completed L Wing Skeleton Riveting - 2.0 hrs
December 23, 2005 - Leveled Wing Spars in Fixture - 1.0 hrs
December 24, 2005 - Wing Walk Doublers - 2.0 hrs
December 31, 2005 - Clecoed on Wing Skins - 2.5 hrs
January 2, 2006 - More Wing Leveling & Drilled Left Wing - 5.0 hrs
January 4, 2006 - Drilled Right Wing & Built Leading Edge Cradle - 3.0 hrs
January 5, 2006 - Clecoed Left Leading Edge - 1.5 hrs
January 6, 2006 - Drilled Left Nose Rib & Plate - 1.5 hrs
January 7, 2006 - Drilled Right Nose Rib & Plate - 1.0 hrs
June 20, 2006 - Back at it! Wing skins clecoed'ed again - 1.5 hrs
June 22, 2006 - Wing Reassembly - 2.0 hrs
September 17, 2006 - Drilled Leading Edge Assemblies - 2.0 hrs
September 19, 2006 - Rough Installed Pitot Mast - 1.5 hrs
September 20, 2006 - Deburred Left Wing Skins - 2.0 hrs
September 21, 2006 - Left Wing Skins Edge Finishing - 1.5 hrs
September 23, 2006 - Dimpled Left Top Wing Skins - 1.0 hrs
September 27, 2006 - Deburred & Dimpled Left Wing Skeleton - 2.0 hrs
September 28, 2006 - Countersunk Left Wing Spar - 1.0 hrs
September 29, 2006 - More Left Spar Countersinking - 2.0 hrs
September 30, 2006 - Joiner Plate, Scarf Joint & Dimpling - 4.0 hrs
October 2, 2006 - Dimpled L Bottom Skins & Deburr LE Parts - 1.0 hrs
October 3, 2006 - Dimpled L Leading Edge Parts - 1.5 hrs
October 4, 2006 - Left Landing/Taxi Light & Leading Edge Prep - 1.5 hrs
October 6, 2006 - Riveted Left Leading Edge - 2.0 hrs
October 7, 2006 - Prep Right Leading Edge Parts - 6.0 hrs
October 8, 2006 - Right Landing/Taxi Light Prep - 1.5 hrs
October 9, 2006 - Riveted Right Leading Edge - 4.0 hrs
October 12, 2006 - Cut Light Hole in Left Leading Edge - 2.0 hrs
October 14, 2006 - Cut Light Hole in Right Leading Edge - 2.5 hrs
October 15, 2006 - Scarf Joint & Right Spar Countersinking - 3.5 hrs
October 17, 2006 - Duburred Right Wing Skins & More Light Prep - 2.5 hrs
October 18, 2006 - Dimpled Right Wing Skins - 1.5 hrs
October 19, 2006 - Cut & Drilled Right Landing Light Lens - 2.0 hrs
October 20, 2006 - Cut & Drilled Left Landing Light Lens - 1.5 hrs
October 24, 2006 - Completed Right Lens - 1.0 hrs
October 25, 2006 - Left Landing Light Lens Re-Do - 1.5 hrs
October 26, 2006 - Riveted Left Leading Edge to Spar - 2.0 hrs
October 27, 2006 - Left Leading Edge Fix - 3.0 hrs
October 28, 2006 - Riveted R LE to Spar & L Wing Skins Clecoed - 8.0 hrs
October 29, 2006 - Prepare and Cleco Right Top Wing Skins - 3.5 hrs
October 30, 2006 - Lighting Experiment - 0.5 hrs
November 9, 2006 - Began Top Wing Skin Riveting - 2.0 hrs
November 11, 2006 - Top Wing Skin Riveting - 8.0 hrs
November 12, 2006 - Completed Riveting Left Top Wing Skins - 2.0 hrs
November 13, 2006 - Reworked Left Tank/LE Seam - 1.5 hrs
November 14, 2006 - Reworked Right Tank/LE Seam - 1.5 hrs
November 15, 2006 - Completed Riveting Right Top Wing Skins - 4.0 hrs
November 18, 2006 - Deconstructed Wing Fixture - 1.5 hrs
November 19, 2006 - Built Wing Cradle - 4.0 hrs
November 25, 2006 - Wing Conduit & Bent Aileron Skins - 2.5 hrs
March 7, 2007 - Started Pushrods - 1.25 hrs
March 13, 2007 - More Pushrods - 1.5 hrs
March 14, 2007 - Primed Large Pushrods - 0.25 hrs
March 15, 2007 - Bellcrank Bushings & Small Pushrods - 1.5 hrs
March 18, 2007 - Painted Small Pushrods - 0.5 hrs
March 25, 2007 - Flap Braces & Small Pushrods - 2.5 hrs
March 29, 2007 - Primed Flap Braces & Drilled Pitot Tube - 2.5 hrs
March 31, 2007 - Miscellaneous Left Wing Work - 2.50 hrs
April 1, 2007 - Miscellaneous Right Wing Work - 3.50 hrs
April 3, 2007 - Left Bottom Skins - Day 1 - 1.5 hrs
April 4, 2007 - Left Bottom Skins - Day 2 - 2.0 hrs
April 6, 2007 - Left Bottom Skins - Day 3 - 1.0 hrs
April 8, 2007 - Left Bottom Skins - Day 4 - 2.0 hrs
April 10, 2007 - Pitot Plumbing & Skin Prep - 1.5 hrs
April 11, 2007 - Left Bottom Skins - Day 5 - 2.0 hrs
April 12, 2007 - Left Bottom Skins - Day 6 - 2.0 hrs
April 14, 2007 - Replaced Aileron Hinge Bracket Washers - 1.0 hrs
April 15, 2007 - Installed Left Landing Light & Project Tour - 0.75 hrs
April 16, 2007 - Random Wing Stuff - 1.0 hrs
April 17, 2007 - Repaired Right Tank Z-Bracket - 1.5 hrs
April 19, 2007 - Right Bottom Skins - Day 1 - 2.0 hrs
April 22, 2007 - Right Bottom Skins - Day 2 - 3.5 hrs
April 23, 2007 - Right Bottom Skins - Day 3 - 1.5 hrs
April 25, 2007 - Right Bottom Skins - Day 4 - 1.0 hrs
April 28, 2007 - Right Bottom Skins - Day 5 - 2.0 hrs
April 29, 2007 - Aileron Bellcranks - 2.0 hrs
April 30, 2007 - Left Aileron Rigging & Flap Install - 1.5 hrs
May 1, 2007 - Deburred & Dimpled W-822PP Access Plates - 0.75 hrs
May 3, 2007 - Access Plates Nutplates - 1.0 hrs
May 9, 2007 - Drilled Left Flap Hinge - 1.5 hrs
May 10, 2007 - Right Aileron & Flap Rigging - 1.5 hrs
May 12, 2007 - Drilled Right Flap Hinge, Installed Flaps, Wings Complete - 3.5 hrs

Fuel Tanks   [TOP]
January 8, 2006 - Started Right Tank & Z-Brackets - 5.0 hrs
January 10, 2006 - Replaced Inboard Z-Bracket - 1.0 hrs
January 14, 2006 - More Z-Brackets & Clecoed Left Tank - 4.0 hrs
January 15, 2006 - Tank Parts - 3.0 hrs
January 17, 2006 - Drilled Left Z-Brackets - 1.0 hrs
January 18, 2006 - Riveted Left Z-Brackets - 2.0 hrs
January 21, 2006 - Various Tank Tasks - 2.5 hrs
January 22, 2006 - Fuel Sender Wiring - 0.5 hrs
June 26, 2006 - Drilled Right Tank - 2.0 hrs
June 27, 2006 - Drilled T-405s - 1.5 hrs
June 28, 2006 - Drilled R Inboard Rib & Capacitive Senders - 1.5 hrs
June 29, 2006 - Riveted R Capacitive Senders & Drilled Access Holes - 1.0 hrs
June 30, 2006 - Tank Inspection Covers - 2.5 hrs
July 1, 2006 - Various Tank Drilling Tasks - 6.0 hrs
July 19, 2006 - Prep Left Tank Skin - 2.0 hrs
July 22, 2006 - Prep Left Tank Parts & Rivet Drain Flange - 3.0 hrs
July 29, 2006 - Rivet Left Tank Cap Flange & Stifferners - 5.0 hrs
July 30, 2006 - Prep Right Tank Parts - 3.0 hrs
July 31, 2006 - Right Tank Drain & Cap Flanges - 1.5 hrs
August 1, 2006 - Riveted Right Tank Stiffeners - 2.0 hrs
August 2, 2006 - Anti Hang-up Brackets - 1.0 hrs
August 3, 2006 - Fuel Tank SB & Prep Ribs - 2.0 hrs
August 5, 2006 - Riveted R Tank Ribs - 5.0 hrs
August 6, 2006 - More R Tank Ribs - 4.0 hrs
August 8, 2006 - Riveted R Tank Outboard Rib - 2.0 hrs
August 9, 2006 - Fabricated Vent & Fuel Return Lines - 2.0 hrs
August 10, 2006 - Sender Issue - 1.0 hrs
August 13, 2006 - Riveted Right Inboard Tank Rib - 2.5 hrs
August 14, 2006 - Right Inboard Fuel Sender Wiring - 1.0 hrs
August 16, 2006 - More Right Tank Wiring & Plumbing - 1.0 hrs
August 18, 2006 - Primed Right Z-Brackets - 1.0 hrs
August 19, 2006 - Riveted Right Tank Baffle - 4.0 hrs
August 21, 2006 - Installed Right Tank Inspection Cover - 1.5 hrs
August 23, 2006 - Anti Hang-up & Inspection Cover (Again) - 1.5 hrs
August 27, 2006 - Began Left Tank - 3.0 hrs
August 28, 2006 - Another Tank Rib - 1.0 hrs
August 29, 2006 - More Tank Ribs - 1.5 hrs
August 31, 2006 - The Last Interior Tank Rib - 1.5 hrs
September 1, 2006 - Left Tank Outboard Rib - 2.0 hrs
September 2, 2006 - Left Tank Plumbing - Leak Test Right Tank - 2.0 hrs
September 3, 2006 - Left Tank Inboard Rib - 2.0 hrs
September 4, 2006 - Left Tank Wiring & Baffle - 4.0 hrs
September 6, 2006 - Installed Left Tank Inspection Cover - 1.0 hrs
September 16, 2006 - Leak Tested Left Tank - 1.0 hrs

Ailerons   [TOP]
November 1, 2006 - Deburred Aileron Brackets - 1.0 hrs
November 3, 2006 - Aileron Stiffeners & Left Spar - 2.5 hrs
November 4, 2006 - Started Right Aileron - 3.0 hrs
November 8, 2006 - Riveted Aileron Stifferners - 1.5 hrs
November 21, 2006 - Drilled Aileron Brackets, Gap Seals & Flap Braces - 3.0 hrs
November 23, 2006 - Primed Aileron Attach Brakets - 2.0 hrs
November 24, 2006 - Riveted Left Aileron Attach Brackets & Gap Seal - 3.0 hrs
November 25, 2006 - Wing Conduit & Bent Aileron Skins - 2.5 hrs
November 28, 2006 - Aileron Skins & Spars - 2.5 hrs
November 29, 2006 - Aileron Drilling - 1.5 hrs
November 30, 2006 - More Aileron Drilling - 1.5 hrs
December 19, 2006 - Aileron Stiffeners (Part Deux) - 1.5 hrs
December 20, 2006 - Edge-Finishing Aileron Stiffeners (Again) - 2.0 hrs
December 21, 2006 - Dimpled Aileron Stiffeners & Skins - 1.5 hrs
December 22, 2006 - Aileron Skin Riveting, Bending & Drilling - 3.0 hrs
December 23, 2006 - Riveted Right Aileron Brackets - 3.0 hrs
January 2, 2007 - Aileron Counterweights - 1.75 hrs
February 6, 2007 - Aileron Deburring & Dimpling - 2.25 hrs
February 7, 2007 - Aileron Edge Finishing - 1.5 hrs
February 10, 2007 - Began Aileron Final Assembly - 4.0 hrs
February 11, 2007 - Riveted Right Aileron - 4.0 hrs
February 14, 2007 - Began Left Aileron Riveting - 1.0 hrs
February 15, 2007 - Left Aileron Complete (Ailerons Done!) - 1.5 hrs

Flaps   [TOP]
December 6, 2006 - Started Right Flap - 1.5 hrs
December 7, 2006 - More Flap Drilling - 1.25 hrs
December 9, 2006 - Flap Shims - 1.5 hrs
December 10, 2006 - Flaps Hinges, Skins & More - 4.5 hrs
December 17, 2006 - Flap Skin Fit Trouble - 0.5 hrs
February 17, 2007 - Bent FL-706Bs - 1.0 hrs
February 20, 2007 - Flap Drilling - 2.0 hrs
February 23, 2007 - Miscellaneous Flap Work - 1.5 hrs
February 24, 2007 - Flap Deburring & Priming - 6.0 hrs
February 25, 2007 - Began Right Flap Riveting - 3.5 hrs
February 27, 2007 - More Right Flap Riveting - 1.25 hrs
February 28, 2007 - Completed Right Flap - 1.0 hrs
March 4, 2007 - Completed Left Flap - 3.0 hrs


Fuselage[TOP]

October 31, 2006 - Ordered Fuselage - 0.0 hrs
December 27, 2006 - Fuselage Arrives - 1.0 hrs
December 28, 2006 - Began Fuselage Inventory - 1.0 hrs
December 30, 2006 - Built Storage for Fuselage Skins - 1.5 hrs
December 31, 2006 - Inventory & Organize Fuselage Parts - 2.0 hrs
January 1, 2007 - Inventory & Organize Fuselage Hardware - 2.5 hrs

Firewall   [TOP]
May 14, 2007 - Began Firewall - 1.75 hrs
May 15, 2007 - Began Fabrication of Firewall Parts - 1.0 hrs
May 16, 2007 - More Firewall Fabrication - 1.5 hrs
May 17, 2007 - Began Firewall Drilling - 0.75 hrs
May 18, 2007 - Finished Firewall Drilling & Fabricated F-601Z - 1.5 hrs
May 20, 2007 - Deburred Firewall Components & Dimpled Firewall - 4.0 hrs
May 22, 2007 - Countersunk Firewall Components - 2.0 hrs
May 24, 2007 - Primed Firewall Components - 1.0 hrs
May 27, 2007 - Riveted Firewall - 4.0 hrs
April 12, 2009 - Riveted Fuel Pump Doubler - 0.50 hrs

Bulkheads   [TOP]
May 28, 2007 - F-704 Bulkhead Work - 3.5 hrs
May 30, 2007 - Control Column Stuff - F-633s & WD-610 - 1.5 hrs
June 2, 2007 - Installed Control Sticks - 1.0 hrs
June 3, 2007 - More F-704 Work - 2.0 hrs
June 6, 2007 - Still More F-704 Work - 2.0 hrs
June 9, 2007 - Riveted Cover Support Ribs & Web Stiffeners to F-704A - 2.5 hrs
June 23, 2007 - Riveted F-704 Parts - 2.0 hrs
June 26, 2007 - F-705 Fabrication - 2.5 hrs
June 30, 2007 - Drilled F-705 Bars - 3.0 hrs
July 1, 2007 - Drilled Seat Belt Anchors - 1.5 hrs
July 4, 2007 - F-705 Parts Fabrication - 2.5 hrs
July 8, 2007 - More F-705 Stuff - 3.0 hrs
July 16, 2007 - Drilled the Slots in the F-705Gs - 1.0 hrs
July 17, 2007 - Miscellaneous F-705 Tasks - 1.5 hrs
July 18, 2007 - Began F-706 Bulkhead - 1.5 hrs
July 21, 2007 - F-706, F-707 and F-708 Bulkheads - 2.5 hrs
July 22, 2007 - Began F-711 Bulkhead - 2.5 hrs
August 5, 2007 - F-710, F-712 Bulkheads & More - 4.0 hrs
August 6, 2007 - Bulkhead Deburring - 1.5 hrs
August 7, 2007 - More Bulkhead Deburring - 2.0 hrs
August 8, 2007 - Bulkhead Deburring Complete - 1.5 hrs
August 9, 2007 - Miscellaneous Bulkhead Stuff - 2.0 hrs
August 11, 2007 - Primed Bulkheads - 4.0 hrs
August 12, 2007 - Began Riveting Bulkheads - 1.0 hrs
August 13, 2007 - Riveted F-706 Bulkhead - 1.5 hrs
August 14, 2007 - Riveted F-711 Bulkhead - 1.5 hrs
August 16, 2007 - Began F-705 Riveting - 1.75 hrs
August 23, 2007 - Completed F-705 Bulkhead - 1.00 hrs

Longerons   [TOP]
August 26, 2007 - Trimmed Longerons - 2.5 hrs
August 28, 2007 - Longeron Bending - Part I - 1.75 hrs
August 30, 2007 - Longeron Bending - Part II - 2.0 hrs
September 4, 2007 - Longeron Bending - Part III - 1.5 hrs
September 9, 2007 - Longeron Bending - Part IV - 1.5 hrs
September 10, 2007 - Drilled Canopy Decks - 1.5 hrs
September 12, 2007 - Longeron Bend and Twist - 1.5 hrs
September 13, 2007 - Trimmed J Stiffeners - 2.25 hrs

Aft Fuselage   [TOP]
September 14, 2007 - Started Aft Fuselage - 1.5 hrs
September 15, 2007 - Began Tail Spring Mount - 4.0 hrs
September 16, 2007 - More Tail Spring Mount & Clecoed Aft Fuselage - 2.5 hrs
September 18, 2007 - Finished Clecoing Aft Fuselage - 1.5 hrs
September 22, 2007 - Drilled J Stiffeners - 3.0 hrs
September 23, 2007 - Drilled Aft Fuselage Skins - 2.0 hrs
September 29, 2007 - Disassembled Aft Fuselage - 0.5 hrs
October 2, 2007 - Deburring Day 1 - 1.5 hrs
October 3, 2007 - Deburring Day 2 - 1.5 hrs
October 7, 2007 - Deburring Day 3 - 3.0 hrs
October 8, 2007 - Deburring Day 4 - 3.0 hrs
October 9, 2007 - Aft Skin Dimpling - 2.0 hrs
October 11, 2007 - Began Aft Fuse Riveting - 1.5 hrs
October 13, 2007 - Aft Fuse Riveting Issues - 1.0 hrs
October 14, 2007 - Bad News - 1.0 hrs
October 23, 2007 - Rebuilt F-712 Bulkhead - 1.0 hrs
October 24, 2007 - Prepared New F-779 Skin - 2.0 hrs
October 25, 2007 - Drilled New F-712 to Side Skins - 1.25 hrs
October 26, 2007 - F-712 to F-779 Riveting - 1.50 hrs
October 28, 2007 - F-711 to F-779 Riveting - 1.50 hrs
November 6, 2007 - Aft Fuselage Riveting - Day 1 - 2.0 hrs
November 9, 2007 - Aft Fuselage Riveting - Day 2 - 2.5 hrs
November 11, 2007 - Aft Fuselage Riveting - Day 3 - 2.5 hrs

Center Fuselage   [TOP]
October 18, 2007 - F-716 Rib Work - 3.5 hrs
October 19, 2007 - More F-716 Rib Stuff - 6.0 hrs
October 21, 2007 - F-776 Bottom Skin & F-623 Corner Ribs - 3.5 hrs
November 4, 2007 - F-623As, F-623Bs & F-704Hs - 3.0 hrs
November 12, 2007 - Center Section Drilling & Deburring - 2.5 hrs
November 18, 2007 - Began Crotch Strap Brackets - 2.0 hrs
November 20, 2007 - Crotch Strap Brackets Day 2 - 0.5 hrs
November 21, 2007 - Crotch Strap Brackets Day 3 - 2.5 hrs
December 2, 2007 - Crotch Strap Brackets Day 4 - 1.0 hrs
December 4, 2007 - Trimmed Seat Belt Anchors - 1.5 hrs
December 5, 2007 - Drilled Flap Bearings - 1.5 hrs
December 6, 2007 - Center Section Deburring - 1.5 hrs
December 9, 2007 - More Center Section Deburring - 2.5 hrs
December 11, 2007 - Primed Seat Ribs - 1.5 hrs
December 12, 2007 - Deburring & Dimpling - 2.0 hrs
December 16, 2007 - More Center Section Stuff - 4.5 hrs
December 26, 2007 - Riveted Seat Ribs to F-704 Bulkhead - 1.25 hrs
December 30, 2007 - Riveted Baggage Ribs to F-705 Bulkhead - 2.5 hrs
January 1, 2008 - Riveted F-776 Center Bottom Skin - 3.0 hrs
January 2, 2008 - Clecoed Floors - 1.5 hrs
January 4, 2008 - Fluted F-715 Seat Ribs - 1.0 hrs
January 5, 2008 - Drilled F-715 Seat Ribs - 3.0 hrs
January 6, 2008 - Notched Longerons - 2.0 hrs
January 8, 2008 - Mated Fuselage Sections - 2.0 hrs
January 9, 2008 - Clecoed F-770 Side Skins - 1.0 hrs
February 10, 2008 - Armrests & Conical Bend #1 - 2.0 hrs
February 17, 2008 - Conical Bend #2 & Longeron Drilling - 3.5 hrs
February 18, 2008 - More Longeron Drilling - 0.75 hrs

Forward Fuselage   [TOP]
February 24, 2008 - Completed Longeron Drilling & Clamped Firewall - 2.50 hrs
March 10, 2008 - Firewall Drilling - 1.50 hrs
March 15, 2008 - Auxillary Longerons & Stiffeners - 3.50 hrs
March 16, 2008 - Completed F-719 Stiffeners - 2.00 hrs
March 23, 2008 - F-717 Longerons - 1.50 hrs
March 30, 2008 - Drill F-717 Longerons to WD-603 Eng Mount Brackets - 3.50 hrs
April 19, 2008 - Drilled F-684 Gussets to Fuse - 3.50 hrs
May 3, 2008 - Shimmed F-7101 & F-902 - 1.50 hrs
May 4, 2008 - Fabricated F-796Cs & F-796Ds - 1.50 hrs
May 9, 2008 - Fabricated F-796Bs - 1.50 hrs
May 11, 2008 - More F-796Bs - 1.00 hrs
May 18, 2008 - F-796Bs Round Two - 3.50 hrs
June 1, 2008 - Deburred Rudder Pedals - 2.00 hrs
June 8, 2008 - Drilled Rudder Pedals - 2.50 hrs
June 19, 2008 - Riveted Rudder Pedals - 2.50 hrs
June 20, 2008 - Rudder Bearing Blocks - 5.00 hrs
June 27, 2008 - Mounted Rudder Pedals - 3.00 hrs
June 28, 2008 - Floor Stiffeners - 5.00 hrs
June 29, 2008 - Baggage Ribs & Miscellaneous Fuselage Drilling - 4.00 hrs
July 6, 2008 - More Fuselage Stuff - 3.00 hrs
July 8, 2008 - A Decision is Made - 0.00 hrs
October 28, 2008 - Back to Work! - 1.50 hrs
October 29, 2008 - Fuselage Disassembly - 1.50 hrs
October 30, 2008 - Fuselage Deburring - 1.00 hrs
October 31, 2008 - F-7101 Work - 1.00 hrs
November 2, 2008 - More Deburring - 4.00 hrs
November 6, 2008 - Deburring - 2.00 hrs
November 9, 2008 - Skin Deburring - 1.50 hrs
November 11, 2008 - Skin Deburring & Edge Finishing - 1.50 hrs
November 16, 2008 - Fuselage Disassembly - 1.00 hrs
February 19, 2009 - Deblueing & Deburring - 1.00 hrs
February 20, 2009 - Deburring & Edge Finishing - 2.00 hrs
February 21, 2009 - Deburred Longerons - 1.50 hrs
February 22, 2009 - Longeron Countersinking - 2.50 hrs
February 26, 2009 - More Countersinking - 1.50 hrs
February 28, 2009 - Began Fuselage Dimpling - 2.50 hrs
March 1, 2009 - More Fuselage Deburring - 2.50 hrs
March 11, 2009 - Dimpled Aft Fuselage - 1.50 hrs
March 14, 2009 - More Fuselage Prep - 3.00 hrs
March 15, 2009 - Primed Longerons - 1.50 hrs
April 15, 2009 - Nutplates & Armrests - 1.50 hrs
April 16, 2009 - Reinforced Armrests - 1.50 hrs
April 17, 2009 - Deburred Forward Bottom Skin - 1.50 hrs
April 19, 2009 - Dimpled Forward Bottom Skin - 1.50 hrs
April 21, 2009 - Began Dimpling of Side Skins - 1.00 hrs
April 23, 2009 - Finished Dimpling Side Skins - 1.00 hrs
April 24, 2009 - Dimpled the Firewall - 1.00 hrs
April 25, 2009 - Cleaned & Primed Fuselage Parts - 3.00 hrs
April 26, 2009 - More Priming & Prep - 2.50 hrs
April 28, 2009 - Painting Parts - 1.50 hrs
April 29, 2009 - Began Fuselage Assembly - 1.00 hrs
May 1, 2009 - Fuselage Assembly Day 2 - 2.00 hrs
May 2, 2009 - Fuselage Assembly Day 3 - 2.50 hrs
May 3, 2009 - Fuselage Assembly Day 4 - 2.50 hrs
May 16, 2009 - Fuselage Riveting Day 1 - 3.00 hrs
May 17, 2009 - Fuselage Riveting Day 2 - 3.00 hrs
May 20, 2009 - Fuselage Riveting Day 3 - 2.50 hrs
May 23, 2009 - Fuselage Riveting Day 4 - 2.00 hrs
May 24, 2009 - Fuselage Riveting Day 5 - 2.00 hrs
May 25, 2009 - Fuselage Riveting Day 6 - 2.50 hrs
May 26, 2009 - Fuselage Riveting Day 7 - 1.50 hrs
June 2, 2009 - Fuselage Riveting Day 8 - 2.00 hrs
June 18, 2009 - Fuselage Update - 3.00 hrs
June 24, 2009 - Ready to Flip - 2.50 hrs
June 25, 2009 - Das Boot! - 0.50 hrs
June 27, 2009 - Technical Inspection #2 - 1.50 hrs
July 20, 2009 - Riveted F-695 Gussets to Fuselage - 3.50 hrs

Aft Deck, Canopy Decks & Top Skins   [TOP]
June 30, 2009 - Drilled the Aft Deck - 1.5 hrs
July 2, 2009 - F-710C and F-711E Spacers - 1.5 hrs
July 3, 2009 - Deburred & Primed Aft Deck Parts - 1.5 hrs
July 7, 2009 - Canopy Decks & F-757s - 1.5 hrs
July 9, 2009 - F-695 Gussets - 2.0 hrs
July 11, 2009 - Various Fuselage Stuff - 5.00 hrs
July 20, 2009 - Riveted F-695 Gussets to Fuselage - 3.50 hrs
July 23, 2009 - Made Two Static Line Clips - 1.00 hrs
July 25, 2009 - More Canopy Deck Work - 2.50 hrs
July 27, 2009 - Riveted F-705G Angles & J Stiffeners Work - 2.00 hrs
July 26, 2009 - Notched F-705G Angles & Clecoed Aft Skin - 2.00 hrs
August 4, 2009 - Riveted F-728 Bellcrank Channel to Fuselage - 1.50 hrs
August 15, 2009 - Drilled F-775 Rear Top Skin - 1.50 hrs
August 16, 2009 - Drilled F-774 Aft Top Skin - 3.50 hrs
September 6, 2009 - Riveted F-656s to F-706 Bulkhead - 1.00 hrs
September 7, 2009 - Deburring & Edge-Finishing - 2.50 hrs
October 29, 2009 - Back to work! - 1.50 hrs
November 2, 2009 - Deburring & Clecoing - 2.50 hrs

Cabin & Seats   [TOP]
November 4, 2009 - Drilled Baggage Area - 1.00 hrs
November 7, 2009 - Riveted Baggage Side Covers - 1.50 hrs
November 8, 2009 - Riveted Baggage Floors - 2.50 hrs
November 28, 2009 - Trimmed and Drilled Upper Baggage Bulkhead - 2.25 hrs
November 29, 2009 - More Upper Baggage Bulkhead - 0.25 hrs
December 3, 2009 - Notched and Final Drilled Upper Baggage Bulkhead - 0.75 hrs
December 23, 2009 - Fabricated F-6114B & C Wear Blocks - 1.50 hrs
December 27, 2009 - More Baggage Bulkhead Work - 1.50 hrs
January 3, 2010 - Baggage Bulkhead Nutplate Installation - 2.00 hrs
February 7, 2010 - Wear Block Installation - 2.00 hrs
February 14, 2010 - Baggage Side Covers - 1.50 hrs
February 15, 2010 - F-637E Seat Hinges - 2.00 hrs
February 21, 2010 - Rivet Seat Hinges - 2.50 hrs
March 7, 2010 - Rivet Aft Seat Floors - 3.00 hrs
April 18, 2010 - Fabricated Tunnel Cover - 2.00 hrs
April 22, 2010 - Installed Floors and Began Seats - 3.00 hrs
April 24, 2010 - Seat Backs - Day 1 - 3.00 hrs
April 25, 2010 - Seat Backs - Day 2 - 3.50 hrs
May 1, 2010 - Seat Backs - Day 3 - 2.50 hrs
May 2, 2010 - Seat Backs - Day 4 - 3.00 hrs
May 3, 2010 - Seat Backs Complete - 1.00 hrs
May 8, 2010 - Center Cabin Cover - 2.50 hrs
May 9, 2010 - Andair Fuel Pump Installation Day 1 - 2.00 hrs
May 16, 2010 - Andair Fuel Pump Installation Day 2 - 1.50 hrs


Other Stuff[TOP]

May 31, 2005 - B-17 & B-24 Visit Livermore
August 24, 2005 - Ride with Dan Checkoway
October 8-11, 2005 - Pismo Beach & Wine Tasting Weekend
December 9, 2005 - Visit with Dawin Barrie
February 17, 2006 - Project Update... Moving
April 21, 2006 - Project Update... Almost Home
July 4, 2006 - Happy 4th of July! (photo mosaic)
July 16, 2006 - Back from Vacation
July 27, 2006 - Airventure 2006
September 24, 2006 - Added Web Site Search
November 5, 2006 - Citabria Flight
February 1, 2007 - Project Update
February 18, 2007 - Builder Assist Day
May 5, 2007 - Lunch Flight to Hollister, CA
July 29, 2007 - Airventure 2007
February 2, 2008 - I'm Not Dead Yet
February 23, 2008 - Project Update
August 14, 2008 - Project Update
February 11, 2009 - Project Status
July 5, 2009 - Reorganized the Shop
August 2, 2009 - Back from AirVenture 2009
September 4, 2009 - Launched AviatorApps.com
December 24, 2009 - Putting my Tools to Good Use
May 12, 2010 - Web Site Changes